annieb-house.blogspot.com
My Housing Project: Swimming Pool
http://annieb-house.blogspot.com/2007/11/swimming-pool.html
Monday, November 5, 2007. The area was ready for installing the system. The water pipes are installed under the concrete floor while they are working on the electrical line. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: Floor Tile
http://annieb-house.blogspot.com/2008/07/floor-tile.html
Wednesday, July 30, 2008. Construction works slowly move on, they finish laying floor tile and the other swimming pool. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: Slowly Move On
http://annieb-house.blogspot.com/2008/08/slowly-move-on.html
Saturday, August 30, 2008. We have a bathroom in 2-story house which intend to be a spa room, so Polished stone or terrazzo is used; floor, wall and bath tub is shaped by hand. Iron parapet is installed on front steps and balcony. Antique stone is selected to make house look more attractive. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: Air Conditioner and Wood Part
http://annieb-house.blogspot.com/2008/05/air-conditioner-and-wood-part.html
Saturday, May 31, 2008. Air Conditioner and Wood Part. We select "Diakin" for our project. As recommended by architect, it will look really nice to use Duct Connection Static Pressure Type that the machine will be installed in the ceiling, although it is much more expensive than ordinary wall type. Some part of the house are real wood, which is touchable. But some part, we change to conwood in order to save the forest. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: 1-Story House : Concrete Floor
http://annieb-house.blogspot.com/2007/11/1-storey-house-concrete-floor.html
Saturday, November 10, 2007. 1-Story House : Concrete Floor. First week of November, 2007, I with an architect, looked over the progress of the construction. The car parking and the bathroom concrete floor of 1-story house were built. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: October 2008
http://annieb-house.blogspot.com/2008_10_01_archive.html
Saturday, October 25, 2008. Piling is done every 1 square meter to prevent subsidence. Concrete road is laid except some areas, front gates and fence, which have to consult the architect. House's picture takes in October 22, 2008. Subscribe to: Posts (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: Stair and Bathroom wall
http://annieb-house.blogspot.com/2008/04/stair.html
Wednesday, April 30, 2008. Stair and Bathroom wall. After electrical conduits are installed, ceiling frame are prepared. Concrete stairs in front of 2-story house are built. Each step is attached to wall without string on the other side. Bathroom wall is attached with tiles. Each bathroom contain different styles so as to different colors. However, beige tone is the basic color with some decoration stones because it provides comfortable feeling. Subscribe to: Post Comments (Atom). Notable Things of Me.
annieb-house.blogspot.com
My Housing Project: Electrical Conduit and Outside Ceiling
http://annieb-house.blogspot.com/2008/03/electrical-conduit-and-ceiling.html
Wednesday, March 26, 2008. Electrical Conduit and Outside Ceiling. The electrical conduit was connected around the houses. Ceiling beams are being constructed. Outdoor ceiling are being constructed under the roof. I am in in front of construction site. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.
annieb-house.blogspot.com
My Housing Project: Door and Window Frame
http://annieb-house.blogspot.com/2008/09/door-and-window-frame.html
Tuesday, September 30, 2008. Door and Window Frame. Door and window frame is another part that moves very very slow. They are working on attaching the aluminum frame, it may take about a few months to complete their work. December 14, 2008 at 3:51 AM. Subscribe to: Post Comments (Atom). Notable Things of Me. View my complete profile.